 | Office building "Le Prélude" | |
The property developer HINES entrusted the Project Management to AURIS. The role consists in the coordination of design team (architect and consultant engineers...
Open realisation  |
|
 | Office Building "L'Angle" | |
The mission of the Project Manager in this case applies to the direction and coordination of the design development phase and to overall management during the c...
Open realisation  |
|
 | Tribunal de Commerce et Conseil de Prud’homme de Bobigny | |
The role of client side technical and cost assistance consists in the critical analyse of the documentation produced by the architect and formulating where nece...
Open realisation  |
|
 | Appartment Building "Les Ateliers du XXème" | |
AURIS has been entrusted with 3 principal roles : Establishment of the Tender and Contract package, Construction Management and coordination of post contract v...
Open realisation  |
|
 | Office Buildings "Les Arcas" | |
The mission of Project Management commenced during the design development phase. It consisted in assuring :
- engineering management : establishment of speci...
Open realisation  |
|
 | Dependant Aged Persons Home « Les Tilleuls » | |
Le Conseil Général des Yvelines (78) called tenders for innovative projects concerning the dependant aged persons homes of the area. Within this context, the re...
Open realisation  |
|
 | Lycée Professionnel « Théodore Monod » et I.U.F.M. « Léon Jouhaux » | |
In response, AURIS undertook a programmatic study, consisting of 2 phases :
1) Pre-Programme which sought to indicate to the client the spacial and organisa...
Open realisation  |
|
 | Boarding School Eugène Napoléon | |
The construction Management of the project particularly concerned sur :
The organisation and time scheduling of the site
Cost effective organisation and con...
Open realisation  |
|
 | Office Building - le Carat 2 | |
Client side technical assistance ensures that the future property owner makes informed decisions during the construction of the acquired project. The organisati...
Open realisation  |
|
 | Lycée Professionnel Saint François d'Assise | |
Our role as client advisor / client representative for the project consisted of :
An audit of the existing buildings
Feasibility study : elaborated in terms o...
Open realisation  |
|
 | Retail Centre « Grand Ciel » | |
- Putting in place the project team and assist Corio with the decisional process undertaken with the co-property owners.
- Direct and coordinate the project t...
Open realisation  |
|
 | Educational Facility Dupanloup | |
The client representative / assistant’s role involves underlining the technical, financial and administrative incidence of proposed architectural solutions to ...
Open realisation  |
|
 | Ecole Nationale d’Administration | |
La mission of Client Representative involved the direction of the project from the feasibility phase to the handover :
- Assisting the client in the elaborati...
Open realisation  |
|
 | Educational Facility Notre-Dame | |
- Conclude property transactions with the local authorities responsible for the “ZAC”.
- Ensure the integration of the 1 470 m² school extension within a proje...
Open realisation  |
|
 | Lower School « zéro énergie » | |
AURIS, as mandated client assumes the following tasks :
- Analysis of project brief and provisional budget
- Confirmation of the time schedule
- Assistance i...
Open realisation  |
|
 | Free way service stations | |
SANEF sought to develop an original concept of a « retail village » capable of being applied to the totality of their freeway network. The retail villages would...
Open realisation  |
|
 | Office Building "Meunier IE" | |
The missions entrusted to AURIS cover:
1) Project Management
2) Construction Management
3) Upfront engineering coordination and synthesis...
Open realisation  |
|
 | Saint –Gobain International Research Campus | |
Auris was chosen to provide complete client representative services, from the the brief development and sketch design phase to the construction and handover pha...
Open realisation  |
|
 | Medical-Social Institute and Specialised Education and Home Care Service | |
The client assistance mission was broken down as follows:
- Preliminary design: prospecting for financing, town planning and land availability feasibility, le...
Open realisation  |
|
 | “Digiteo Labs” research centre, Palaiseau (91) | |
The mandated site management mission was broken down as follows:
- Supervision of project manager’s studies: analysis of preliminary design and project stud...
Open realisation  |
|
 | “Le Khapa” office building, Boulogne (92) | |
The mission given to the Technical Project Manager concerned the management and coordination of the design studies as from the works phase and included all the ...
Open realisation  |
|
 | Office building in Montigny-le-Bretonneux (78) | |
The mission given to AURIS concerned the management and coordination of design studies as from the detailed design phase and works supervision through to the co...
Open realisation  |
|
 | “Axe Seine” office building, Nanterre (92) | |
The mission given to the Technical Project Manager concerned the management and coordination of design studies as from the detailed design phase and all buildin...
Open realisation  |
|
 | “Les Hautes Terres” housing block, Noisy-le-Grand (93) | |
The mission given to AURIS began during the building permit phase
Our main missions: preparation of the contractor tender files, works supervision.
...
Open realisation  |
|
 | “Le Clos du Village” housing block, Créteil (94) | |
Auris was chosen to carry out a Technical Client Assistance mission from the negotiation phase through to the delivery phase, as well as assist the client in it...
Open realisation  |
|
 | “L’Opale” office buildings - ZAC Walwein, Montreuil (93) | |
AURIS was chosen to carry out a complete client assistance mission from the detailed design phase through to the construction phase and the handover of the work...
Open realisation  |
|
 | “Anthos” office building - ZAC Seguin, Boulogne (92) | |
The mission given to the Technical Project Manager concerned the supervision of building works, in coordination with the operation’s architect and the various e...
Open realisation  |
|
 | Marne-La-Vallée University Library (77) | |
- Control over all operational expenses and organisation of the approved and pending phases,
- Organisation of intervening parties (preparation of the project...
Open realisation  |
|
 | Shops in Orgeval (78) | |
Our mission incorporated the following aspects:
- Design management:
. Preparation of the contract specifications
. Engineering
- Surveying
- General wor...
Open realisation  |
|
 | Interministerial restaurant, Paris, 7th arrondissement | |
Our client representative mission is broken down as follows:
- Analysis of the programme and budget estimate, ascertaining technical and functional feasibil...
Open realisation  |
|
 | “BAYER – A” high rise office building in Puteaux (92) | |
The mission given to AURIS concerns the management and coordination of the design studies as from sketch design phase, followed by works management through to c...